Cause: Utility company's power failure.

Settlement: £142,000

Case summary

One of our visual effects companies suffered a power surge and failure due to works undertaken by their utility provider resulting in damage to their technical equipment and business interruption.

How we helped?

Together with the client we were able to demonstrate to Insurers the extent of the financial loss suffered due to the downtime and settlement was agreed at the full amount.